This is a CBS home that is being built in Cape Coral Florida. (Please follow along on the different phases of construction)
360 Walk Through          3D Floor Plan       2D Floor Plan
Follow along  the construction of this home with  this photo pictorial  from start to finish.
 
Gabbard Residence
Days Under Construction (120)
Home Finished October 17 2008

This CBS home has just started construction in Cape Coral Florida. It is being built on a gorgeous oversized home site with a intersecting basin view. This gulf access lot is complete w/ 10k lift and dolphin cradle waiting for a boat.

While building a new home is both exciting and rewarding it also demands that a buyer be fully prepared and committed to the challenge. We are the experts and are fully committed in finding you a beautiful lot and a qualified builder that will build you the finest quality home possible and provide you with a positive experience in the process. That is our goal. There is no cost to you for our services, we work off the offered commission split provided by the seller and or builder,

Our clients have invited you to follow along and watch all the different stages of construction
as their CBS home is being built.

This site offers you the ability to walk through their virtual home, view a 3d floor plan and follow the construction process with up to date photos.

Tamure' Corporation will be doing a virtual  walk through tour once the
Gabbards have time to furnish their home. So please check back soon.
 

If you would like to know what prices are like for waterfront lots and what it would cost to build a new CBS home in our area please contact Steve Tate at the numbers below or go to the
contact page for client references and testimonials.


PLEASE NOTE:
This site was designed and is maintained by Tamure. Tamure’ is a licensed real estate corporation in the state of Florida. This site is an advertising promotion for Tamure’ Corporation and is not intended to show that Tamure Corporation is the Builder or Contractor in any matter. 

 

 

 

 

 

 

 

 

 

 

 

 

 

800-582-6873

Tamure' Corporation
3444 Marinatown Lane Suite 5
North Fort Myers, Florida 33903
Telephone:(239)995-6262   Fax: (239) 995-6186

Tamure' is a licensed real estate corporation
in the state of Florida

This Site was designed and is maintained by  David Rumbold.
If you have any questions or comments about our site,
please E-Mail me at Dave@tamure.com

Time Table

Date:2007  Search for waterfront Lot
Date:12/14/07 Contact for Lot
Date:1/07/08  Closed on lot contract.


Date: 3/01/08  Started negotiation on home contract with builder .

Date: 6/23/08
 Started construction of home. First stage clearing lot preparing for footer.

Date: 7/03/08 Footer dug, digging pool and laying CBS block (Garage walls) Cement floor has not been poured yet.

Date: 7/12/08 Cement floor has been poured. The cement pool shell is finished.

Date: 7/20/08 CBS Walls are finished now working on Tie Beam.

Date: 7/24/08 Trusses are up, waiting for roof dry-in.

Date: 7/29/08 Working on dry-in. Plywood going on.

Date: 8/01/08  Dry-in just about finished. Interior walls going up.

Date: 8/07/08 Working on air conditioning duct work, doors and windows. Water pipes in.

Date: 8/20/08 Electric has been installed. Getting ready for stuccoing.

Date: 8/27/08 Insulation has been installed. Outside stucco has been applied. Shingles or on the roof waiting to be installed.

Date: 8/30/08 Working on drywall, cove molding and sliding glass doors

Date: 9/05/08 Working hard coating drywall, installing interior trim base boards and interior doors, installing brick coping around pool.

Date: 9/11/08 Starting cabinet work in home.

Date: 9/12/08 Finished installing tile in bathrooms. Painting outside of home.
Finishing up cabinet work in home.

Date: 9/19/08 Finished trim work on front entrance. Finished driveway paver bricks. Working on finishing tile on roof.

Date: 9/25/08 Installing light fixtures, counter tops and living fireplace.

Date: 9/27/08 Working on pool deck.

Date: 10/01/08 Working on landscaping, fireplace and range hood.

Date: 10/17/08 Home is now finished.