This is a CBS home that is being built in Cape Coral Florida. (Please follow along on the different phases of construction)
Follow along the construction of this home with this photo
pictorial from start to finish.
|
|
|
Gabbard
Residence Days Under Construction (120) Home Finished October 17 2008 This CBS home has just started construction in Cape Coral Florida. It is being built on a gorgeous oversized home site with a intersecting basin view. This gulf access lot is complete w/ 10k lift and dolphin cradle waiting for a boat. While building a new home is both exciting and rewarding it also demands that a buyer be fully prepared and committed to the challenge. We are the experts and are fully committed in finding you a beautiful lot and a qualified builder that will build you the finest quality home possible and provide you with a positive experience in the process. That is our goal. There is no cost to you for our services, we work off the offered commission split provided by the seller and or builder, Our clients have invited you to follow along and watch all the different
stages of construction
Tamure' Corporation will be doing a virtual walk through tour once
the
If you would like to know what prices are like for waterfront lots and
what it would cost to build a new CBS home in our area please contact
Steve Tate at the numbers below or go to the
800-582-6873
Tamure' Corporation
This Site was designed and is maintained by David
Rumbold. |
Time Table Date:2007 Search for waterfront Lot Date: 3/01/08 Started negotiation on home contract with builder . Date: 7/12/08 Cement floor has been poured. The cement pool shell is finished. Date: 7/20/08 CBS Walls are finished now working on Tie Beam. Date: 7/24/08 Trusses are up, waiting for roof dry-in. Date: 7/29/08 Working on dry-in. Plywood going on. Date: 8/01/08 Dry-in just about finished. Interior walls going up. Date: 8/07/08 Working on air conditioning duct work, doors and windows. Water pipes in. Date: 8/20/08 Electric has been installed. Getting ready for stuccoing. Date: 8/27/08 Insulation has been installed. Outside stucco has been applied. Shingles or on the roof waiting to be installed. Date: 8/30/08 Working on drywall, cove molding and sliding glass doors Date: 9/05/08 Working hard coating drywall, installing interior trim base boards and interior doors, installing brick coping around pool. Date: 9/11/08 Starting cabinet work in home. Date:
9/12/08 Finished installing tile in bathrooms. Painting outside
of home. Date: 9/19/08 Finished trim work on front entrance. Finished driveway paver bricks. Working on finishing tile on roof. Date: 9/25/08 Installing light fixtures, counter tops and living fireplace. Date: 9/27/08 Working on pool deck. Date: 10/01/08 Working on landscaping, fireplace and range hood. Date: 10/17/08 Home is now finished. |